Construction Loan Calculator
Calculate construction loan interest-only payments during the build phase and permanent mortgage payments after conversion.
Construction Loan Calculator
Calculator
Adjust values & calculateEnter your values below. Every result is computed in your browser — no data is sent to any server.
Formula: Interest-Only (construction): Interest = Drawn Amount x Rate / 12 | Permanent: M = P[r(1+r)^n]/[(1+r)^n-1]
Worked example — ~$1,625/mo during build, $2,528/mo permanent
Formula
Interest-Only (construction): Interest = Drawn Amount x Rate / 12 | Permanent: M = P[r(1+r)^n]/[(1+r)^n-1]
During construction, you pay interest-only on drawn funds. Draws typically follow a schedule (e.g., 10% at start, then periodic draws). After construction, the loan converts to a standard amortizing mortgage.
Worked Examples
Example 1: $400K construction
Problem:$400K budget, 7.5% construction rate, 12mo, then 6.5% permanent 30yr
Solution:Avg construction interest: ~$1,625/mo. Permanent: $2,528/mo
Result:~$1,625/mo during build, $2,528/mo permanent
Frequently Asked Questions
How do construction loan draws work?
The lender releases funds in stages (draws) as construction progresses — typically foundation, framing, dry-in, interior, and final. You only pay interest on the amount drawn so far.
What is a construction-to-permanent loan?
A one-time-close loan that converts from a construction loan to a permanent mortgage after building is complete. You only pay closing costs once, unlike two separate loans.
What are the typical down payment requirements for a construction loan?
Construction loans typically require a larger down payment than traditional mortgages, usually 20-25% of the total project cost (land plus construction). Some lenders accept the land as part of the equity contribution if you already own it free and clear. FHA construction loans allow as little as 3.5% down for eligible borrowers. The higher down payment requirements exist because construction loans carry more risk — the collateral (the finished home) does not yet exist, and construction projects can face cost overruns, delays, or contractor issues.
What costs are typically included in a construction loan budget?
A construction loan budget should include land acquisition (if not already owned), architect and design fees, building permits and impact fees, site preparation and grading, foundation work, framing, roofing, plumbing, electrical, HVAC, insulation, drywall, flooring, cabinets and countertops, fixtures and appliances, exterior finishes, landscaping, and a contingency reserve of 10-15% for unexpected costs. Soft costs like loan origination fees, interest reserves, and title insurance are also typically included. Most lenders require a detailed line-item budget and cost breakdown from a licensed general contractor before approving the loan.
Why do construction loan rates price above the permanent mortgage rate?
During the build the lender's collateral is an unfinished structure, so it carries completion risk on top of credit risk: if the borrower or contractor fails mid-project, the half-built house is worth far less than the funds advanced. Construction notes are also usually short-term and floating, often quoted as a spread over prime, rather than a fixed 30-year rate. That combination typically puts the construction rate one to two points above the permanent rate.
What is an interest reserve, and how does it change what you pay each month?
An interest reserve is a line inside the loan budget that the lender draws on to pay construction-phase interest for you, rather than billing you monthly. It smooths cash flow while you may still be paying rent or an existing mortgage, but it is borrowed money: the reserve increases the drawn balance, so interest accrues on interest, and the total rolls into the permanent loan at conversion. Ask whether your interest is billed or reserved before comparing quotes.
How does a draw inspection work before the lender releases funds?
Each draw request is matched against a schedule of values, the line-item cost breakdown supplied by the general contractor, using forms such as AIA G702 and G703. The contractor certifies the percentage of each line completed, an inspector or third-party service verifies the work on site, and the lender releases funds for completed work only, frequently holding back retainage until final completion. Lien waivers from subcontractors are usually required with each request.
What is the difference between a one-time-close and a two-close construction loan?
A one-time-close, or construction-to-permanent, loan sets both the construction terms and the permanent mortgage at a single closing, then converts automatically once the certificate of occupancy is issued. A two-close structure funds the build first, then requires a separate refinance into the permanent mortgage. Two closings mean a second set of closing costs and a second underwriting, during which a rate move or a change in your income or credit could raise the payment or block approval.
What happens to carrying cost if the build runs long or over budget?
Every extra month of construction is another month of interest on a balance that is near its peak, so delays are expensive at exactly the point where they cost most. Cost overruns are usually covered first by the contingency reserve of roughly 10 to 15 percent built into the budget; beyond that you fund change orders from cash, since lenders rarely increase the committed amount. Many notes also charge an extension fee if construction runs past the maturity date.
Why is average construction interest roughly half the interest on the full budget?
Construction Loan Calculator assumes a linear draw curve, so the balance in month m is the budget times m divided by the number of months. Averaging that fraction across the term gives (n+1)/2n, which approaches one half for a typical twelve-month build. Month one therefore costs very little and the final month costs close to full-balance interest. Real draws are lumpy rather than linear, and a front-loaded schedule pushes actual interest above this estimate.
References
Background & Theory
History
Reviewed for accuracy by Sahil, Senior Finance & Tax Editor · Editorial policy
Related Calculators
🚗Auto Loan Calculator
Calculate car loan payments and interest
🚤Boat Loan Calculator
Calculate boat financing payments
🏢Business Loan
Estimate monthly payments, total interest, and amortization for business loans including SBA, term, and line of credit options
🏠FHA Loan Calculator
Calculate FHA loan payments and costs
💳Loan Calculator
Calculate monthly payments, total interest, and payoff time for any loan
⚖️Loan vs Invest Decision Helper
Compare paying off debt vs investing with after-tax analysis
💵Personal Loan
Estimate monthly payments and total cost of a personal loan by entering amount, rate, and term to compare lending options
🧮Loan Payment Calculator with Amortization
Calculate loan payment with inputs, formulas, and instant results.