Gravel Driveway Calculator
Calculate gravel needed for your driveway including base and surface layers. Estimate tons, cubic yards, truck loads, and total installation cost.
Gravel Driveway Calculator
Calculator
Adjust values & calculateEnter your values below. Every result is computed in your browser โ no data is sent to any server.
Formula: Volume = Length x Width x (Total Depth / 12) / 27; Tons = Cu Yd x Density
Worked example โ 11.11 cubic yards, 15.56 tons, 2 truck loads
Formula
Volume = Length x Width x (Total Depth / 12) / 27; Tons = Cu Yd x Density
Calculate the driveway area by multiplying length by width in feet. The total depth combines the base layer and top layer thicknesses. Convert depth from inches to feet by dividing by 12, then multiply by the area to get cubic feet. Divide by 27 to convert to cubic yards, and multiply by density to get tons.
Worked Examples
Example 1: Standard Two-Car Driveway
Problem:Calculate gravel for a 50 ft x 12 ft driveway with 4-inch base and 2-inch top layer.
Solution:Area = 50 x 12 = 600 sq ft Total depth = 6 inches = 0.5 ft Volume = 600 x 0.5 = 300 cu ft = 11.11 cu yd Tons = 11.11 x 1.40 = 15.56 tons Truck loads = 2
Result:11.11 cubic yards, 15.56 tons, 2 truck loads
Example 2: Long Rural Driveway
Problem:Calculate gravel for a 200 ft x 10 ft driveway with 4-inch base and 2-inch top.
Solution:Area = 200 x 10 = 2,000 sq ft Total depth = 6 inches = 0.5 ft Volume = 2,000 x 0.5 = 1,000 cu ft = 37.04 cu yd Tons = 37.04 x 1.40 = 51.85 tons Truck loads = 6
Result:37.04 cubic yards, 51.85 tons, 6 truck loads
Frequently Asked Questions
How thick should a gravel driveway be?
A properly constructed gravel driveway should be 6 to 8 inches thick in total, built in multiple layers. The bottom layer should be 4 inches of larger crushed stone such as number 3 stone (1.5 to 2 inches) that provides a stable foundation and promotes drainage. The middle layer is 2 inches of mid-size stone like number 57. The top layer is 2 inches of finer material such as crusher run that compacts into a smooth driving surface. Each layer should be compacted with a roller or plate compactor before adding the next layer.
How much does a gravel driveway cost to install?
A gravel driveway typically costs between $1.50 and $5.00 per square foot for materials and installation, with an average cost of $1,500 to $5,000 for a standard two-car driveway. Material costs run $25 to $55 per ton depending on the gravel type. Professional installation including grading, geotextile fabric, and compaction adds $1.00 to $3.00 per square foot. Delivery charges average $50 to $150 per truckload. The total cost depends heavily on your location, existing grade conditions, and whether drainage work is needed.
How long does a gravel driveway last?
A well-built gravel driveway can last 10 to 15 years or more with proper maintenance. The base layer is essentially permanent and rarely needs replacement. The top surface layer typically needs refreshing every 2 to 5 years by adding 1 to 2 inches of new material and regrading. Regular maintenance includes raking loose gravel back toward the center, filling potholes, and regrading with a box blade or road grader after heavy rains. Installing proper drainage and edging significantly extends the lifespan and reduces maintenance.
Do I need a geotextile fabric under my gravel driveway?
Geotextile fabric is strongly recommended under gravel driveways, especially on soft or clay soils. The fabric acts as a separation barrier that prevents gravel from sinking into the soil below, which is the primary cause of driveway failure. It also distributes load weight more evenly and inhibits weed growth. Woven geotextile fabrics are best for driveways because they provide higher tensile strength. The fabric typically costs $0.15 to $0.50 per square foot and can reduce annual gravel replacement costs by 30 to 50 percent over the life of the driveway.
How do I convert cubic yards of gravel into tons?
Multiply cubic yards by the aggregate's density in tons per cubic yard. Crusher run runs about 1.40 tons per cubic yard, #57 stone and pea gravel about 1.35, and river rock about 1.50. A 50 by 12 foot driveway at 6 inches total depth is 600 square feet times 0.5 feet, or 300 cubic feet, which is 11.1 cubic yards; at 1.40 tons per cubic yard that is roughly 15.6 tons.
What is the difference between crusher run and #57 stone?
Crusher run is a graded aggregate containing everything from roughly three-quarter inch stone down to fines and stone dust. Those fines fill the voids so the material locks up tightly under a compactor and sheds water, making it the right choice for a driving surface. #57 stone is washed and single-sized with the fines removed, so it drains freely but never binds. Use #57 for drainage layers and crusher run for the wearing course.
How much extra gravel should I order to allow for compaction?
Aggregate delivered loose loses volume when it is rolled, because the fines migrate into the voids between larger stones. As a planning rule, order roughly 10 to 15 percent more than the finished in-place volume when the material will be mechanically compacted, and place it in lifts of about 4 inches so the compactor can reach the full depth. Ordering exactly the geometric volume almost always leaves the driveway short of its design thickness.
Why does pea gravel make a poor driving surface?
Pea gravel is naturally rounded and washed free of fines, so the stones have no angular faces to interlock and no binder to hold them together. Under tyre loads the particles simply roll aside, forming ruts and pushing material to the shoulders. It is comfortable underfoot and fine for pathways or drainage trenches, but a driving surface needs angular crushed stone with fines, such as crusher run, over a coarser base course.
How many truckloads will my gravel order need?
Delivery is priced per load, not per ton, so tonnage is rounded up to whole trucks. A tandem-axle dump truck typically carries on the order of ten to fifteen tons depending on local axle-weight limits, while a tri-axle carries more. Dividing your total tonnage by the truck capacity and rounding up gives the load count, and each partial load still costs a full delivery fee, so slightly increasing an order is often cheaper per ton.
What crown or cross slope should a gravel driveway have?
A gravel driveway must shed water sideways or it will hold moisture, soften the base and form potholes. The standard practice for unpaved surfaces is a crown of roughly 4 percent, about half an inch of fall per foot measured from the centreline to each edge, paired with shallow ditches or a positive slope away from the edge. Crown is lost as traffic displaces material, so it should be re-established when the surface is regraded.
References
Background & Theory
History
Reviewed for accuracy by Abdullah, Technical Content Specialist ยท Editorial policy
Related Calculators
๐งฎConcrete Driveway Cost Calculator
Calculate concrete driveway cost with inputs, formulas, and instant results.
๐งฎConcrete Driveway Volume Calculator
Calculate concrete driveway volume with inputs, formulas, and instant results.
๐งฎConcrete Driveway Calculator
Calculate concrete volume, cost, and reinforcement for a new driveway by dimensions.
๐งฎCement Calculator
Calculate cement with inputs, formulas, and instant results.
๐งฎConcrete Cure Time Estimator
Calculate concrete cure time estimator with inputs, formulas, and instant results.
๐งฎConcrete Estimator Tube
Calculate concrete estimator tube with inputs, formulas, and instant results.
๐งฎConcrete Formwork Area Calculator
Calculate concrete formwork area with inputs, formulas, and instant results.
๐งฎConcrete Mix Design Calculator
Calculate concrete mix design with inputs, formulas, and instant results.