Concrete Volume Footings Calculator
Free Concrete volume footings Calculator for cement & concrete projects. Enter dimensions to get material lists and cost estimates.
Formula
Rectangular: V = L x W x D; Cylindrical: V = pi x r^2 x D; Total = V x Qty x (1 + Waste%)
Where L, W, D are length, width, and depth in feet, r is the radius for round footings, Qty is the number of footings, and Waste% accounts for spillage and over-excavation. Divide total cubic feet by 27 to get cubic yards.
Worked Examples
Example 1: Four Rectangular Deck Footings
Problem: Calculate concrete needed for 4 rectangular footings, each 24 x 12 x 8 inches, with 10% waste.
Solution: Per footing volume = (24/12) x (12/12) x (8/12) = 2 x 1 x 0.667 = 1.333 cu ft\nTotal volume = 1.333 x 4 = 5.333 cu ft\nWaste (10%) = 0.533 cu ft\nTotal with waste = 5.867 cu ft\nCubic yards = 5.867 / 27 = 0.22 cu yd\n80-lb bags needed = ceil(5.867 / 0.6) = 10 bags
Result: Total: 5.87 cu ft (0.22 cu yd) | 10 bags (80-lb) needed
Example 2: Six Round Sonotube Footings
Problem: Calculate concrete for 6 cylindrical footings with 12-inch diameter and 36-inch depth, 10% waste.
Solution: Radius = (12/12) / 2 = 0.5 ft\nPer footing = pi x 0.5^2 x (36/12) = 3.14159 x 0.25 x 3 = 2.356 cu ft\nTotal volume = 2.356 x 6 = 14.137 cu ft\nWaste (10%) = 1.414 cu ft\nTotal with waste = 15.551 cu ft\nCubic yards = 15.551 / 27 = 0.576 cu yd\n80-lb bags = ceil(15.551 / 0.6) = 26 bags
Result: Total: 15.55 cu ft (0.58 cu yd) | 26 bags (80-lb) needed
Frequently Asked Questions
How do you calculate concrete volume for footings?
Concrete volume for footings is calculated by determining the volume of each individual footing and multiplying by the total number of footings needed. For rectangular footings, multiply length times width times depth to get cubic inches, then convert to cubic feet by dividing by 1,728 or convert each dimension to feet first. For cylindrical footings like Sonotubes, use the formula pi times radius squared times depth. Always add a waste factor of 5 to 10 percent to account for spillage, uneven subgrade, and over-excavation. The total volume in cubic feet is then divided by 27 to convert to cubic yards, which is the standard ordering unit for ready-mix concrete trucks. One cubic yard fills approximately 27 cubic feet of space.
What size footings do I need for my project?
Footing size depends on the load they must support and the bearing capacity of your soil. Building codes typically require footings to be at least 12 inches wide for one-story structures and 15 to 24 inches wide for two-story buildings. Depth requirements vary by region based on frost line depth, which ranges from 12 inches in warm climates to 48 inches or more in northern regions. The footing thickness, or height, is usually at least 6 to 8 inches for residential construction and must be at least as thick as the projection beyond the foundation wall. For deck posts, 12-inch diameter cylindrical footings are common for standard loads, while larger 16 to 24 inch footings are used for heavy structures or weak soils. Always consult local building codes and a structural engineer.
Should I use ready-mix concrete or bags for footings?
The choice between ready-mix concrete delivered by truck and bagged concrete mix depends on the total volume needed and project logistics. For small projects requiring less than one cubic yard (about 27 cubic feet), bagged concrete is usually more practical and cost-effective. Each 80-pound bag yields approximately 0.6 cubic feet of concrete. For projects requiring more than one to two cubic yards, ready-mix delivery is significantly more efficient and provides better consistency. Ready-mix concrete typically costs 120 to 160 dollars per cubic yard delivered, while bagged concrete costs roughly 150 to 200 dollars per cubic yard when you factor in the labor of mixing. Ready-mix also ensures proper water-to-cement ratio and uniform strength throughout the pour.
How much waste factor should I add to concrete calculations?
A waste factor of 5 to 10 percent is standard for most concrete footing projects, but certain conditions warrant higher percentages. For footings poured directly against soil (without forms), add 10 to 15 percent because the rough excavation walls absorb concrete and create an irregular shape. For formed footings with smooth walls, 5 percent waste is usually sufficient. Sloped sites may require 15 to 20 percent extra due to uneven depths. When ordering ready-mix, always round up to the nearest quarter or half yard because running short during a pour creates cold joints that weaken the structure. It is far better to have a small amount of leftover concrete than to stop mid-pour. Excess concrete can be used for small projects like stepping stones or splash blocks.
What concrete mix strength should I use for footings?
For residential footings, a minimum concrete strength of 2,500 PSI is required by most building codes, but 3,000 to 4,000 PSI is recommended for better durability and load-bearing performance. Standard ready-mix concrete is typically delivered at 3,000 PSI, which is suitable for most residential and light commercial footings. In areas with sulfate-rich soil, Type II or Type V sulfate-resistant cement should be specified to prevent chemical deterioration. For cold weather pouring, specify air-entrained concrete with 5 to 7 percent air content to resist freeze-thaw cycling. The water-to-cement ratio should not exceed 0.50 for footings in contact with soil. Higher PSI ratings like 4,000 or 5,000 are used for commercial buildings, heavy equipment pads, and footings in challenging soil conditions.
How do I calculate the amount of concrete needed for a project?
Calculate volume in cubic feet (length x width x depth), then divide by 27 to convert to cubic yards. Add 5-10% for waste and spillage. One cubic yard of concrete covers 81 square feet at 4 inches thick.